Am Lemmchen school site: New high school building, replacement elementary school, Realschule Plus, canteen and sports halls

Aerial view of the Lemmchenschule

Brief description

Construction has begun on a new high school in Mainz-Mombach. The four-track high school, which opened in September 2023 in a temporary building on Lerchenberg, is designed as a “school with a special inclusive profile” and serves as a shared learning environment for students with and without disabilities.
The high school’s future location will be in Mombach at “Am Lemmchen,” alongside the schools already located there today (the elementary school and the Realschule Plus). These, along with a cafeteria and a sports hall with six courts, will be newly constructed after the high school’s completion, creating a modern school campus for all age groups.
The high school moved into the modular building at the “Am Lemmchen” site shortly before the summer break in 2024. Classes began there on the first day of the 2024–25 school year. The cafeteria has been in operation since early April 2024 and is used by the high school students.

Citizen participation

  • On July 5, 2023, Marianne Grosse, then head of the Department of Construction, hosted an initial public information session at the school site. The minutes of the event can be found at the bottom of this page in the download section.
  • On March 20, 2024, a construction site tour was held for interested citizens and residents. A total of approximately 200 people participated in the three tours. The minutes of the event can be found at the bottom of this page in the download section.
  • The construction site blog has been online since February 2024 as another component of public information and is accessible via the following link: Construction Site Blog for the Am Lemmchen School Site

Further public participation events are planned. The dates will be published here.

Affected urban area

Mainz-Mombach

Planned planning and implementation period

  • On September 4, 2023, the new high school, with its unique inclusive focus, began the new school year at its temporary location in Lerchenberg.
  • The high school’s move from Mainz-Lerchenberg to Mainz-Mombach took place in mid-July 2024. Classes began on August 26, 2024, at the modular school.
  • Due to an objection to the building permit, construction could not begin as planned in the summer of 2025. The objection was rejected in December 2025.
  • The high school is scheduled to be completed and ready for use by the 2029–30 school year. Subsequently, the elementary school, the Realschule Plus, the cafeteria, and the gyms will be newly constructed.

Expected costs

131 million euros according to cost estimate as of December 2022

Current processing status (February 20, 2026)

The temporary building and the temporary cafeteria are now open.

download area

Contact us

Address

Building management Mainz

Zitadelle, Bau E
Am 87er Denkmal
55131 Mainz

Postal address

P.O. Box 3820
55028 Mainz

Explanations and notes

Picture credits

Sprachauswahl

Quick search